Project description:
Municipal waste water treatment plant extension - site supervision
Country:
Czech Republic
City:
Brno
Completed:
2008
End customer:
Brněnské vodárny a kanalizace
Project description
The project Reconstruction and Extension of WWTP for Brno city in Modřice was executed by a Czech-French consortium of companies ONDEO-Degrémont, Aquatis Brno (GP), Imos Brno and ŽS Brno in years 2001 – 2004.
CHETENG Engineering, s.r.o. provided their specialists´ services to the investor (WWTP) in the project team (PIU) where they supervised the project documentation of the construction in the mechanic-technological part, erection, electro and measuring and regulation (MaR). At implementation of the construction itself, they performed the job of the investor´s technical control at which they supervised conformity of the works executed with project documentation and the executed jobs´ quality itself.
In the warranty period of 2005 – 2008, CHETENG Engineering, s.r.o. provided the investor with technical assistance in the field of technical inspections of the construction to reveal and evaluate faults in the construction part and to supervise their elimination.
Parameters of the newly reconstructed WWTP:
WWTP: meets the effluent standards required by the European Union – 1.0 mg P/l and 10 mg N/l.
CHETENG Engineering, s.r.o. provided their specialists´ services to the investor (WWTP) in the project team (PIU) where they supervised the project documentation of the construction in the mechanic-technological part, erection, electro and measuring and regulation (MaR). At implementation of the construction itself, they performed the job of the investor´s technical control at which they supervised conformity of the works executed with project documentation and the executed jobs´ quality itself.
In the warranty period of 2005 – 2008, CHETENG Engineering, s.r.o. provided the investor with technical assistance in the field of technical inspections of the construction to reveal and evaluate faults in the construction part and to supervise their elimination.
Parameters of the newly reconstructed WWTP:
- population equivalent: 513 300 PE
- total design daily flow: 137 000 m3/day
- average hourly flow: 5 708 m3/hour
- maximum dry weather flow: 7 600 m3/hour
- maximum rain weather flow: 15 200 m3/hour
WWTP: meets the effluent standards required by the European Union – 1.0 mg P/l and 10 mg N/l.
Licensor:
COWI Group
Capacity:
137 000 m³/d